Keeping a Commercial Fit-Out on Schedule

Home/Blog/Commercial

Sequencing, long-lead items and why the ceiling grid decides more of your programme than you think.

A commercial fit-out is a sequencing problem more than a building one. Dozens of trades share the same floor, most of them need something another trade has to finish first, and the landlord’s handover date does not move.

The ceiling grid sets the pace

Sprinklers, lighting, air conditioning, data and access control all live in the ceiling void, and the grid cannot close until every one of them is in and tested. Coordinate the ceiling first and the rest of the programme tends to follow. Three habits keep it that way:

Handover is a stage, not a day

Snagging, commissioning and the operation and maintenance manuals take weeks, not days. Plan them as a stage with its own dates and the client moves into a finished space rather than a working site.

Search

Need help with your project?

Talk to a project manager, not a salesperson. We will tell you what the work really involves.

Our Blog

Related Articles

Practical guidance from our project managers on planning, budgeting and getting the build right.

Prefabrication, low-carbon concrete and on-site data are changing how buildings get built — and what they cost.

Six questions that separate a contractor who will finish your project from one who will start it.

Where renovation budgets actually go, and the five decisions worth making before anyone picks up a tool.